Phase 2, Stage 14 2001/2002

Stage 6 Aston Clinton by-pass diversion (500m)
The work on the Aston Clinton Bypass was started in October 2001.

{short description of image} {short description of image} {short description of image} {short description of image}
November 2001: The Canal at the bottom of the Aston Clinton Bypass. November 2001: Looking down at the canal from the bypass. February 2002: The current lay of the canal. The bypass work in the background. February 2002: The base for the new bridge is in place.
{short description of image} {short description of image} {short description of image} {short description of image}
May 2002: The canal and towpath can be seen between the walls of the new bridge. The top of the new by-pass bridge has been done. Oct 2002: The new Aston Clinton by-pass bridge is taking shape and the new wing walls are in and the brick work on one side is done. Oct 2002: Balfour beatty have stared the laying of the Bentomat linein.

Phase 2, Stage 14

Phase 2, Stage 14A

Return to Phase2

Return to Index