Phase 2, Stage 5 Progress Report
Click on picture to enlarge it. Use the back button to get back to this page or open in a new window.Or it may open in a new window. Just close it.
Stage 5 (2009/2010) is the fifth of six main stages of relining the dry canal bed ready for re-watering and is 350 metres long and includes a 50m reinforced concrete towpath wall to form a short term mooring
Clearance towards Whitehouses has been completed.
September 2000: The excavator arrives at stage 5. | January 2001: Clearing of stage 5 completed. |