Phase 2, Stage 5 Progress Report

Click on picture to enlarge it. Use the back button to get back to this page or open in a new window.Or it may open in a new window. Just close it.

Stage 5 (2009/2010) is the fifth of six main stages of relining the dry canal bed ready for re-watering and is 350 metres long and includes a 50m reinforced concrete towpath wall to form a short term mooring

Clearance towards Whitehouses has been completed.

To see an archive of the pictures of th this stage, clicke work on here

{short description of image} {short description of image}
September 2000: The excavator arrives at stage 5. January 2001: Clearing of stage 5 completed.