Phase 2, Stage 1 Progress Report

Click on picture to enlarge it. Use the back button to get back to this page or open in a new window.Or it may open in a new window. Just close it.

Stage 1 (2005/2006) is the first of six main stages of relining the dry canal bed ready for re-watering and is 321 metres long and includes a 50m reinforced concrete towpath wall to form a short term mooring, one of four such moorings to be provided under Phase II.

CC's boundary to manhole E of Drayton B'champ Bridge No.5

The length has already been cleared. It requires annual striming of weeds.

{short description of image}

{short description of image}

November 2001: Stage 4 has been cleared, but already it is begining to grow over again.

Mar 2003: We did are annual striming of weeds and stumping with BITM.

2005

Since April 2005, we have excavated the first fifty metres and also capped the old pipeline under the canal with a concrete raft.

{short description of image}

{short description of image}

{short description of image}

APRIL 2005. Work begins on Phase 2.

Oct 2005.
Excavated up to the sump at Drayton Beauchamp

Oct 2005.We have lined the first bit connecting to the work already done at Drayton Beauchamp

{short description of image}

{short description of image}

{short description of image}

{short description of image}

Aug 2006.A 14ft narrow has been constructed at the old sump and lined for10 metres

Sep 2006. The first lined length.

March 2007.
pipe capping .

March 2007.now in the pipe capping.

{short description of image}

{short description of image}

{short description of image}

{short description of image}

October 2007.
The next lined length..

December 2007: Now in water.

January 2008: One of the new moringbays is set out.

{short description of image} {short description of image} {short description of image} {short description of image}
{short description of image} {short description of image} {short description of image}